Tuesday, February 10, 2009

Update 17

Last week was a busy one, with adding yet more parts to the #1 engine. I sorted out which carburetor airbox went to which engine (via trying them out...)

I still need to rig the prop governor, which turns out to be kind of "special".



I installed the fuel strainer and primer pump on the nacelle support structure. It's really starting to take shape now.



I installed the Carb Temp Sensors in all the carburetors.



Last (and probably least), I paneled up the #1 nacelle.


Some of the panels will need some work to make them fit better, which is why I thought I should try them out now, rather than later...

Monday, February 2, 2009

100 visitors!

Hey, just thought I would post that this blog has now been visited by 100 different visitors!

Update 16

Last week saw the hatch put to bed, so to speak.



I painted all the parts up real pretty.



and installed them.



After testing it a lot (a whole lot) of times, and fiddling with the adjustments, finally I was satisfied that the functioning was repeatable and positive.



It's now on for good.

I even cleaned and waxed the windows. (there was some pretty old masking tape on them)



I started working on the Stabilizer trim system.

This is the forward segment of the Stab Trim Driveshaft.

Monday, January 26, 2009

Update 15

That's alotta updates!

Last week, I assembled the various pieces/parts to secure the hatch to the cockpit.



The cable and sleeves arrived and I'm carefully squeezing the cables together. There is no provision for adjustment, so I need to get it right the first time. (or at least the second time...)



I'm not sure what the reasoning was behind not using turnbuckles, but it sure looks nice and clutter free like this.

In other areas, I routed a bunch of teleflex cables for the engine controls. This was a real safari.



Turns out, I really should know better than to think I can simply believe the labels that were carefully attached to the various parts. I also should ignore the hardware that was installed presumably in the same holes from which it was previously removed...



Once I was able to dispatch such things from my mind, the pile of parts sort of assemble themselves.



Frankly, the fact that all the brackets for the hatch were labeled "R" , in theory, meaning "Right side" and that none were labeled "L" for left should have been an omen to me.

The big news for the coming week is the arrival of "2 carloads" of Trimotor rebuilders from Port Clinton, OH. I'll be hosting them on Saturday for a tour of N8419. I hope this meeting to be a spark plug for both airplanes, igniting renewed vigor and fresh perspective to each project.

Monday, January 19, 2009

Update 14

Good Monday Morning, Trimotor fans!

I hope everybody received some good exercise while shoveling snow over the weekend. I know I did. (my apologies to readers from warmer climes who do not have the privilege of participating in such enjoyment).

As you may recall from the previous post, I found a real challenge in the Emergency Hatch. You'll be happy to read (and see) that the challenge has for the most part passed.







The hatch fits the cockpit structure quite well now, and I have made what parts were missing by copying the parts that were not missing.


Amazing what you can do with simple hand tools (and time)
Hand tools may be our friends, but time is not.

I have ordered the cable and nicopress sleeves necessary to complete the release mechanism, and it should be here this week sometime.

Now for the next challenge, whatever that may be...

Monday, January 12, 2009

Update 13

Good morning Trimotor fans. I hope you had a productive and restful weekend.

Last week, some amount of time was spent seeking the next biggest stumbling block to the timely completion of the project.

Whattayaknow, I found it:




That's right, the emergency hatch fits not-so-good.



It also has no attachment type fittings installed, nor any holes for, well, anything.


There is a box of fittings, links, handles, etc. that obviously goes with the hatch:

I couldn't help but laugh at the text on the box. Heh, did the writer intend to say that there is no way that these bits will function? Perhaps they meant that they didn't begin assembling the bits?
Time will tell.

It does have some rivets in a pattern similar to the fittings, and I'll use the "puzzle" method to get it together.

So far, the above bracketry is, unfortunately, the brightest aspect of this task.




the light coming through the cracks is the darkest aspect.
heh, poetic, eh?

Not to worry, as there is a plan. I'll be sure and keep this blog's readers updated as the plan is adapted.

Monday, January 5, 2009

Update 12

Welcome, readers to update number 12.

I hope everyone out there had a happy and safe new year. The days are getting longer, and the project is progressing.

Last week was engine indicating line week. In particular, routing the lines that go from the lower portion of the #2 firewall,



over the rudder pedal enclosure,






to the upper portion, which is the instrument "enclosure".




Turns out, when you have 3 engines, there are a passel of indicators, and low and behold, a #3 line for each one. Naturally, there are quite a few Adel clamps used to secure said lines. Anyone that has had the pleasure of finagling a clamp into a place where it didn't really "want" to go can appreciate the installation of 62 of those little gems on this short section of lines.